Building 10
11/06/2017

The new sidewalk will be formed and poured on Monday and Tuesday. Work will begin to prepare the soil along the retaining wall early in the week and new ferns will be planted late in the week. The entire project should be complete by 11/10.

NCRC Building 10 Entrance Landscaping Improvements.

 

U-M Grounds will be performing a landscape improvement project at the building 10 entrance. This project will improve the sustainability of plantings, improve the egress path from the north Atrium area, and reduce ongoing maintenance.  The project also increases no mow areas at NCRC further reducing our carbon footprint.

   
 The project will begin the week of November 1 and continue for approximately two weeks.  

 Expect increased contractor activity along the North windows of the ground floor of building 10.